Monday, October 29, 2018

 

 

 Good News!!! The project is completed and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the current status of the project and upcoming work.
The Village of Glenview will provide surveys in the coming weeks for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.


Thanks again for all your patience and understanding throughout the construction project. We hope that you are happy with the improvements made.


If you have any questions or concerns, please feel free to contact Tim Schwister, Village Project Manager, at 847-904-4422.


Friday, October 5, 2018

The roadways included in Stage 2 include:

·        Le High Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Le High Avenue to Patriot Boulevard
 

 

Work Anticipated to be performed, October 8 to October 12th

 
·        The project is substantially complete. the only activity will be various punch list items throughout the project.
 
 
 

THNAK YOU to everyone for their patience and understanding throughout the project

Friday, September 21, 2018

The roadways included in Stage 2 include:

·        Le High Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Le High Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, September 24th to September 28th.

 
·       Paving completed this week on LeHigh and Compass.
 
  • Striping on Lehigh and Compass to tentatively begin next week.
 
 

There will be no full roadway closures, although travel delays are expected as the work is performed.

Friday, September 14, 2018

The roadways included in Stage 2 include:

·        Le High Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Le High Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, September 17th to September 211st.

 
·       Landscaping should be completed on Monday, weather permitting
  • Monday / Tuesday Le High and Compass will be oiled prior to paving. Please keep in mind that once the road is oiled, please drive slowly in the oiled areas, to help prevent the oil from sticking to your cars.
  • Tuesday Paving surface will commence, starting at Le High and Patriot and working to the South.
 

 

There will be no full roadway closures, although travel delays are expected as the work is performed.

I would like to say Thank You in advance for your patience.

Sunday, September 9, 2018

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, September 10th to September 14th.

 
·       Structure adjustments to begin on Monday for all of next week
  • Road Patching and Driveway patching to begin tentatively end of next week
 

 

There will be no full roadway closures, although travel delays are expected as the work is performed.

I would like to say Thank You in advance for your patience.

Friday, August 31, 2018

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, September 4th to September 7th.

 
·       Tentatively starting to mill the project Tuesday Sept. 4
  • once milled the contractor will b e raising structures to apply the final Bituminous Surface
 

 

There will be no full roadway closures, although travel delays are expected as the work is performed.

I would like to say Thank You in advance for your patience.

We would like to wish everyone a safe and happy Labor Day weekend!!



 

 

Friday, August 24, 2018

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, August 27th to August 31st

 
·       Finish lowering structures on Lehigh
  • Tentatively starting to mill the project late next week
 

 

There will be no full roadway closures, although travel delays are expected as the work is performed.

I would like to say Thank You in advance for your patience.

 

Friday, August 17, 2018

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, August 20th to August 24th

 
·       Manhole adjustments throughout Lehigh and Compass
  • Tentatively starting to mill the project late next week
 

 

There will be no full roadway closures, although travel delays are expected as the work is performed.

I would like to say Thank You in advance for your patience.

 

Friday, August 10, 2018

Continuing Curb and sidewalk replacement in phase II



 

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, August 13th to August 17th

 
·        Curb and Gutter and sidewalk removal and replacement WILL continue through the next week.

 

There will be no full roadway closures, the travel delays are expected as the work is performed.

I would like to say Thank You for your patience in advance.

 

Friday, August 3, 2018

Curb, gutter and sidewalk removal and replacement begins next week


Next week the contractor will be installing message signs stating the work on Stage 2 will begin on August 6th.  The road work will begin following the Glenview Park District Triathlon.

 

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, August 6th to August 10th

·        Saw cutting of the curbs in stage 2 on Monday August 6.

·        Curb and Gutter and sidewalk removal and replacement starting Tuesday and continuing through the next week to ten days

 

There will be no full roadway closures, the travel delays are expected as the work is performed.

I would like to say Thank You for your patience in advance.

 

Friday, July 27, 2018

Work to Resume Week of August 6th

Next week the contractor will be installing message signs stating the work on Stage 2 will begin the week of August 6th.  The road work will begin following the Glenview Park District Triathlon.

The roadways included in Stage 2 include:
·         Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard
·         Compass Drive from Lehigh Avenue to Patriot Boulevard

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

There will be no full roadway closures, the travel delays are expected as the work is performed.

Sunday, July 15, 2018

Project on Hold until Early August due to Events in The Glen

Work Performed:
·         Phase I construction completed along Shermer Road, West Lake Avenue, and The Glen Town Center

Work to be Performed
·         No work is scheduled for the project until after August 6th due to the Park Center Triathlon event the previous weekend.
·         The final phase of construction (Phase II) includes Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard and Compass Road from Patriot Boulevard to Lehigh Avenue.

Friday, June 29, 2018

Colored and Stamped Crosswalks and Landscape Restoration On-Going.

Work Performed Last Week, June 25th to June 29th
·         The Glen Town Center
o   Colored and stamped cross-walk installation.
o   Landscape restoration
o   General site clean-up
o   Removal of construction signs
·         West Lake Avenue
o   Completed concrete curb at West Lake and Lily
o   Landscape restoration
o   General site clean-up
o   Removal of construction signs.

Work Anticipated to be performed next week, July 2nd to July 9th  
·         Pavement striping of drive lanes within The Glen Town Center
·         General Site Clean-Up

Due to planned events between July 4th and early August in The Glen area, Stage 2 of the resurfacing will not be started until after August 6th.  We anticipate it will take approximately 2 months to complete this work.  Stage 2 includes Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard and Compass Road from Patriot Boulevard to Lehigh Avenue.

Have a save and enjoyable July 4th Holiday.

Monday, June 18, 2018

Stage 1 Paving Completed!!! Work in The Glen Town Center continues.

Work Performed Last Week, June 11th to June 15th
·         The Glen Town Center, Phase II: Tower Drive (Navy Boulevard to West Lake Avenue), Navy Boulevard, Valor Drive, Sable Drive, Chestnut Drive:
o   Milled the existing pavement surface for drive lanes and parking lanes
o   Adjusted structures in preparation for asphalt paving
o   Paved asphalt surface layer.
o   Installed pavement marking in parking stalls.
·         West Lake Avenue:
o   Paved new asphalt surface
o   Installed pavement markings, with exception of “no parking” hatching.
o   Performed HMA patching at various location where concrete work was performed previously.

Work Anticipated to be performed next week, June 18th to June 22nd
·         The Glen Town Center:
o   Colored and stamped cross-walk installation.
o   Landscape restoration
o   General site clean-up
·         West Lake Avenue
o   Complete concrete curb at West Lake and Lily
o   Landscape restoration
o   General site clean-up
·         Shermer Road
o   Landscape restoration
o   General site clean-up.
 
The first stage of construction is substantially completed with the exception of work in The Glen Town Center, landscape restoration, site clean-up, and other miscellaneous items.  It is not anticipated there will be any further parking restrictions within The Glen Town Center as the paving is completed and parking stalls are striped.

During the installation of the colored and stamped cross-walks, there will only be one travel lane open and traffic will be controlled with flaggers for both directions to utilize one lane.

We are hoping a majority of the work in The Glen Town Center is completed prior the first summer concert at Navy Park. If work is not completed, we are committed to ensure minimal disruption to the event.

The Village is also evaluating the “no parking” hatching along West Lake Avenue to ensure the proper sight distances are maintained while maximizing the parking stalls to the greatest extent possible. The “no parking” hatching will not be completed until the proper studies have been performed and recommendations provided to the Village for consideration.  

The next stage of construction along Lehigh Avenue (East Lake Avenue bridge to Patriot Boulevard) and Compass Road (Patriot Boulevard to Lehigh Avenue) will not begin until after the July 4th Holiday.

Thanks again for all your patience and understanding as you travel along the roadways under construction and The Glen Town Center.

Friday, June 8, 2018

Phase II Glen Town Center Resurfacing to Begin. West Lake Avenue to be Paved.

Work Performed Last Week, June 4th to June 8th  
·         The Glen Town Center, Phase I: Tower Drive (Navy Boulevard to Chestnut Avenue), Aviator Lane, Wolverine Drive.
o   Mill the existing pavement surface of drive lanes and parking lanes
o   Adjusted structures.
o   Paved new asphalt surface
o   Pavement markings within parking stalls, work started but not finished due to rain event on Friday. Work re-scheduled for next week.
·         West Lake Avenue
o   Completed concrete curb & gutter installation
o   Milled existing asphalt surface
o   Performed necessary patching of asphalt pavement
o   Driveway restoration to retail center and Commuter parking lot near Lily Lane
·         Shermer Road
o   Started landscape restoration work.  Due to time of the year, topsoil and seed will be installed.

Work Anticipated to be performed next week, June 11th to June 15th  
·         The Glen Town Center, Phase II: Tower Drive (Navy Boulevard to West Lake Avenue), Navy Boulevard, Valor Drive, Sable Drive, Chestnut Drive
o   Mill the existing pavement surface of drive lanes and parking lanes (Monday & Tuesday)
o   Adjust structures in preparation for asphalt paving (Tuesday & Wednesday)
o   Pave surface, depending on work progress (Thursday & Friday)
o   Pavement Marking of parking stalls (Friday)
·         West Lake Avenue
o   Pave new asphalt surface (Monday). This work was delayed due to patching required near Lily Lane
o   Pavement Marking
 
Parking Restrictions during construction:
·         The Glen Town Center, Phase II
o   No on-street parking while work is on-going, typically 6:00 AM to 5:00 PM
o   Parking will be allowed when work is not in progress and during nights and weekends.
o   Parking Garages will have access at all times.
o   Areas south of Navy Boulevard will be striped with access to parking.
·         West Lake Avenue
o   No on-street parking while work is on-going, typically 6:00 AM to 5:00 PM
o   Parking will be allowed when work is not in progress and during nights and weekends.

The Glen Town Center is scheduled to be completed in late June. We anticipate all of the paving and parking stalls to have pavement marking; however, there might be some additional work to be completed after the July 4th Holiday.

Tuesday, June 5, 2018

The Glen Town Center and West Lake Avenue Pavement Resurfacing Begins. Shermer Road Pavement Completed.

Work Performed Last Week, May 29th to June 1st
·         The Glen Town Center
o   Structure Adjustments prior to pavement milling
·         West Lake Avenue & Lilly Lane
o   Complete storm sewer installation
o   Pour concrete curb & gutter
·         Poppy Lane
o   Pour concrete curb & gutter 

Work Anticipated to be performed next week, June 4th to June 7th
·         The Glen Town Center, Phase I: Tower Drive (Navy Boulevard to Chestnut Avenue), Aviator Lane, Wolverine Drive
o   Mill the existing pavement surface of drive lanes and parking lanes (Monday)
o   Adjust structures in preparation for asphalt paving (Tuesday thru Thursday)
o   Pave surface, depending on work progress (Friday)
·         West Lake Avenue
o   Complete concrete curb & gutter installation (Monday)
o   Mill existing asphalt surface (Tuesday)
o   Adjust structures prior to paving (Wednesday)
o   Pave Surface, depending on work progress (Thursday)
·         Shermer Road
o   Pavement Markings
o   PAVEMENT WORK COMPLETED!!! 

Parking Restrictions during construction:
·         The Glen Town Center, Phase I
o   No on-street parking while work is on-going, typically 7:00 AM to 4:00 PM
o   Parking will be allowed when work is not in progress and during nights and weekends.
o   Parking Garages will have access at all times.
o   Areas north of Navy Boulevard are not affected at this time.
·         West Lake Avenue
o   No on-street parking while work is on-going, typically 7:00 AM to 4:00 PM
o   Parking will be allowed when work is not in progress and during nights and weekend. 

Shermer Road resurfacing is now completed with the exception of punch list items and landscape restorations.  The pavement markings were installed earlier this week. Please be cautious as you drive along the roadway, as there is a tendency to drive faster than the posted speed limit on a newly paved roadway.

Thanks again for all your patience and understanding as you drive through The Glen and deal with the various parking restrictions.