The Glen Town Center
o Structure
Adjustments prior to pavement milling
·
West Lake Avenue & Lilly Lane
o Complete
storm sewer installation
o Pour
concrete curb & gutter
·
Poppy Lane
o Pour
concrete curb & gutter
Work Anticipated to be performed next week, June 4th
to June 7th
·
The Glen Town Center, Phase I: Tower Drive (Navy
Boulevard to Chestnut Avenue), Aviator Lane, Wolverine Drive
o Mill the existing pavement
surface of drive lanes and parking lanes (Monday)
o Adjust structures in
preparation for asphalt paving (Tuesday thru Thursday)
o Pave surface, depending on
work progress (Friday)
·
West
Lake Avenue
o Complete concrete curb &
gutter installation (Monday)
o Mill existing asphalt surface
(Tuesday)
o Adjust structures prior to
paving (Wednesday)
o Pave Surface, depending on
work progress (Thursday)
·
Shermer Road
o Pavement
Markings
o PAVEMENT WORK COMPLETED!!!
Parking Restrictions during construction:
·
The
Glen Town Center, Phase I
o No on-street parking while
work is on-going, typically 7:00 AM to 4:00 PM
o Parking will be allowed when
work is not in progress and during nights and weekends.
o Parking Garages will have
access at all times.
o Areas north of Navy Boulevard
are not affected at this time.
·
West
Lake Avenue
o No on-street parking while
work is on-going, typically 7:00 AM to 4:00 PM
o Parking will be allowed when
work is not in progress and during nights and weekend.
Shermer
Road resurfacing is now completed with the exception of punch list items and
landscape restorations. The pavement
markings were installed earlier this week. Please be cautious as you drive
along the roadway, as there is a tendency to drive faster than the posted speed
limit on a newly paved roadway.
Thanks
again for all your patience and understanding as you drive through The Glen and
deal with the various parking restrictions.