Work to Resume Week of August 6th

Next week the contractor will be installing message signs stating the work on Stage 2 will begin the week of August 6th.  The road work will begin following the Glenview Park District Triathlon.

The roadways included in Stage 2 include:
·         Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard
·         Compass Drive from Lehigh Avenue to Patriot Boulevard

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

There will be no full roadway closures, the travel delays are expected as the work is performed.