The roadways included in Stage 2 include:
· Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard
· Compass Drive from Lehigh Avenue to Patriot Boulevard
Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.
Work Anticipated to be performed, August 20th to August 24th
· Manhole adjustments throughout Lehigh and Compass
- Tentatively starting to mill the project late next week
There will be no full roadway closures, although travel delays are expected as the work is performed.
I would like to say Thank You in advance for your patience.