Friday, September 21, 2018

The roadways included in Stage 2 include:

·        Le High Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Le High Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, September 24th to September 28th.

 
·       Paving completed this week on LeHigh and Compass.
 
  • Striping on Lehigh and Compass to tentatively begin next week.
 
 

There will be no full roadway closures, although travel delays are expected as the work is performed.