The Glen Town Center
o Colored
and stamped cross-walk installation.
o Landscape
restoration
o General
site clean-up
o Removal
of construction signs
·
West Lake Avenue
o Completed
concrete curb at West Lake and Lily
o Landscape
restoration
o General
site clean-up
o Removal
of construction signs.
Work Anticipated to be performed next week, July 2nd
to July 9th
·
Pavement striping of drive lanes within The Glen
Town Center
·
General Site Clean-Up
Due to planned events between July 4th and early
August in The Glen area, Stage 2 of the resurfacing will not be started until
after August 6th. We anticipate it will take approximately 2
months to complete this work. Stage 2 includes Lehigh Avenue from East
Lake Avenue Bridge to Patriot Boulevard and Compass Road from Patriot Boulevard
to Lehigh Avenue.
Have a save and enjoyable July 4th Holiday.