Friday, September 21, 2018

The roadways included in Stage 2 include:

·        Le High Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Le High Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, September 24th to September 28th.

 
·       Paving completed this week on LeHigh and Compass.
 
  • Striping on Lehigh and Compass to tentatively begin next week.
 
 

There will be no full roadway closures, although travel delays are expected as the work is performed.

Friday, September 14, 2018

The roadways included in Stage 2 include:

·        Le High Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Le High Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, September 17th to September 211st.

 
·       Landscaping should be completed on Monday, weather permitting
  • Monday / Tuesday Le High and Compass will be oiled prior to paving. Please keep in mind that once the road is oiled, please drive slowly in the oiled areas, to help prevent the oil from sticking to your cars.
  • Tuesday Paving surface will commence, starting at Le High and Patriot and working to the South.
 

 

There will be no full roadway closures, although travel delays are expected as the work is performed.

I would like to say Thank You in advance for your patience.

Sunday, September 9, 2018

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, September 10th to September 14th.

 
·       Structure adjustments to begin on Monday for all of next week
  • Road Patching and Driveway patching to begin tentatively end of next week
 

 

There will be no full roadway closures, although travel delays are expected as the work is performed.

I would like to say Thank You in advance for your patience.

Friday, August 31, 2018

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, September 4th to September 7th.

 
·       Tentatively starting to mill the project Tuesday Sept. 4
  • once milled the contractor will b e raising structures to apply the final Bituminous Surface
 

 

There will be no full roadway closures, although travel delays are expected as the work is performed.

I would like to say Thank You in advance for your patience.

We would like to wish everyone a safe and happy Labor Day weekend!!



 

 

Friday, August 24, 2018

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, August 27th to August 31st

 
·       Finish lowering structures on Lehigh
  • Tentatively starting to mill the project late next week
 

 

There will be no full roadway closures, although travel delays are expected as the work is performed.

I would like to say Thank You in advance for your patience.

 

Friday, August 17, 2018

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, August 20th to August 24th

 
·       Manhole adjustments throughout Lehigh and Compass
  • Tentatively starting to mill the project late next week
 

 

There will be no full roadway closures, although travel delays are expected as the work is performed.

I would like to say Thank You in advance for your patience.

 

Friday, August 10, 2018

Continuing Curb and sidewalk replacement in phase II



 

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, August 13th to August 17th

 
·        Curb and Gutter and sidewalk removal and replacement WILL continue through the next week.

 

There will be no full roadway closures, the travel delays are expected as the work is performed.

I would like to say Thank You for your patience in advance.