Work Performed This Week, April 23rd to April 27th
·         Road Construction Ahead and Message Boards installed along the project site to inform patrons and traveling public of upcoming work.

Work Anticipated to be performed next week, April 30th to May 4th.
·         Glen Town Center, Phase I of curb & gutter replacement (West side of Tower Drive from Navy Boulevard to Chestnut Avenue):
o   All parking in this area will be restricted starting on Monday, April 30th.  It is anticipated parking will be re-established in 1-2 weeks once curb & gutter replacement is completed.  (Weather dependent)
o   Monday – Saw-Cut areas for curb & gutter replacement
o   Tuesday – Remove existing Concrete Curb & Gutter and install forms for new curb & guttter
o   Wednesday & Thursday – Pour Concrete curb & gutter
o   Curing of concrete curb & gutter as required until parking spaces can be re-opened.
·         Shermer Road (West Lake Avenue to northerly Village Limits)
o   Concrete curb & gutter replacement on one side of the street
·         West Lake Avenue (Patriot Boulevard to Lehigh Avenue)
o   Concrete curb & gutter replacement on one side of the street

We have been able to talk to several businesses along Tower Drive to discuss the upcoming improvements and potential impacts of construction.  If you would like to discuss further, please contact Joe Molidor, project manager, listed on the right side of the page.

As the construction begins, there will be an increase of construction traffic along each of the roadways. We appreciate your patience and understanding as the construction work is performed.