Friday, July 27, 2018

Work to Resume Week of August 6th

Next week the contractor will be installing message signs stating the work on Stage 2 will begin the week of August 6th.  The road work will begin following the Glenview Park District Triathlon.

The roadways included in Stage 2 include:
·         Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard
·         Compass Drive from Lehigh Avenue to Patriot Boulevard

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

There will be no full roadway closures, the travel delays are expected as the work is performed.

Sunday, July 15, 2018

Project on Hold until Early August due to Events in The Glen

Work Performed:
·         Phase I construction completed along Shermer Road, West Lake Avenue, and The Glen Town Center

Work to be Performed
·         No work is scheduled for the project until after August 6th due to the Park Center Triathlon event the previous weekend.
·         The final phase of construction (Phase II) includes Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard and Compass Road from Patriot Boulevard to Lehigh Avenue.