Friday, May 11, 2018

Curb and Gutter continues in The Glen Town Center. Paving on Shermer Scheduled

Work Performed This Week, May 7th to May 11th
·         Curb & Gutter Replacement:
o   Glen Town Center, Phase I & II including both sides Tower Drive from Navy Boulevard to Chestnut Avenue, south side of Navy Boulevard, south side of Sable Drive, Valor Drive)
o   Shermer Road
o   West Lake Avenue
·         Structure adjustments:
o   Phase I and II of The Glen Town Center
o   Shermer Road
o   West Lake Avenue
·         Milling of existing pavement
o   Shermer Road, from West Lake Avenue to norther Village limits.

Work Anticipated to be performed next week, May 14th to May 18th
·         Curb & Gutter Replacement:
o   Glen Town Center, Phase III – West side of Tower Drive from Navy Boulevard to West Lake Avenue
·         Asphalt Surface Paving:
o   Shermer Road
·         Structure adjustments
o   Shermer Road
o   The Glen Town Center, Phase III curb & gutter area
·         Storm Sewer Installation
o   West Lake Avenue at Poppy Lane

Thanks for your patience and understanding as traveling through the project site has been difficult along with the decreased parking stalls within The Glen Town Center. Next week, travelling along West Lake Avenue near Poppy Lane will be especially difficult due to the storm sewer work at that intersection.  One lane of traffic will remain open; however, some travel delays are possible.

Friday, April 27, 2018

Curb and Gutter Replacement to Begin April 30th

Work Performed This Week, April 23rd to April 27th
·         Road Construction Ahead and Message Boards installed along the project site to inform patrons and traveling public of upcoming work.

Work Anticipated to be performed next week, April 30th to May 4th.
·         Glen Town Center, Phase I of curb & gutter replacement (West side of Tower Drive from Navy Boulevard to Chestnut Avenue):
o   All parking in this area will be restricted starting on Monday, April 30th.  It is anticipated parking will be re-established in 1-2 weeks once curb & gutter replacement is completed.  (Weather dependent)
o   Monday – Saw-Cut areas for curb & gutter replacement
o   Tuesday – Remove existing Concrete Curb & Gutter and install forms for new curb & guttter
o   Wednesday & Thursday – Pour Concrete curb & gutter
o   Curing of concrete curb & gutter as required until parking spaces can be re-opened.
·         Shermer Road (West Lake Avenue to northerly Village Limits)
o   Concrete curb & gutter replacement on one side of the street
·         West Lake Avenue (Patriot Boulevard to Lehigh Avenue)
o   Concrete curb & gutter replacement on one side of the street

We have been able to talk to several businesses along Tower Drive to discuss the upcoming improvements and potential impacts of construction.  If you would like to discuss further, please contact Joe Molidor, project manager, listed on the right side of the page.

As the construction begins, there will be an increase of construction traffic along each of the roadways. We appreciate your patience and understanding as the construction work is performed.

Thursday, April 5, 2018

Welcome to our Blog!!!

Welcome to our Blog!!!
Welcome to the Glen Main Stem Roads Resurfacing Construction Blog!!!

These blog posts are meant to provide information regarding the work completed the previous week, work anticipated to be completed the upcoming week, and other pertinent information. Posts are typically created once per week, usually on Friday’s, and as needed to provide additional information regarding the work progress.

We understand that traveling along the roadways during the construction will be challenging and delays are expected. Please understand we will do everything possible to minimize these delays to the greatest extent possible.

We hope you find the information contained in the blogs useful and helpful during the construction process. Please check back often for updates.

Thank you in advance for your patience and understanding.