Friday, August 31, 2018

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, September 4th to September 7th.

 
·       Tentatively starting to mill the project Tuesday Sept. 4
  • once milled the contractor will b e raising structures to apply the final Bituminous Surface
 

 

There will be no full roadway closures, although travel delays are expected as the work is performed.

I would like to say Thank You in advance for your patience.

We would like to wish everyone a safe and happy Labor Day weekend!!



 

 

Friday, August 24, 2018

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, August 27th to August 31st

 
·       Finish lowering structures on Lehigh
  • Tentatively starting to mill the project late next week
 

 

There will be no full roadway closures, although travel delays are expected as the work is performed.

I would like to say Thank You in advance for your patience.

 

Friday, August 17, 2018

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, August 20th to August 24th

 
·       Manhole adjustments throughout Lehigh and Compass
  • Tentatively starting to mill the project late next week
 

 

There will be no full roadway closures, although travel delays are expected as the work is performed.

I would like to say Thank You in advance for your patience.

 

Friday, August 10, 2018

Continuing Curb and sidewalk replacement in phase II



 

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, August 13th to August 17th

 
·        Curb and Gutter and sidewalk removal and replacement WILL continue through the next week.

 

There will be no full roadway closures, the travel delays are expected as the work is performed.

I would like to say Thank You for your patience in advance.

 

Friday, August 3, 2018

Curb, gutter and sidewalk removal and replacement begins next week


Next week the contractor will be installing message signs stating the work on Stage 2 will begin on August 6th.  The road work will begin following the Glenview Park District Triathlon.

 

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, August 6th to August 10th

·        Saw cutting of the curbs in stage 2 on Monday August 6.

·        Curb and Gutter and sidewalk removal and replacement starting Tuesday and continuing through the next week to ten days

 

There will be no full roadway closures, the travel delays are expected as the work is performed.

I would like to say Thank You for your patience in advance.

 

Friday, July 27, 2018

Work to Resume Week of August 6th

Next week the contractor will be installing message signs stating the work on Stage 2 will begin the week of August 6th.  The road work will begin following the Glenview Park District Triathlon.

The roadways included in Stage 2 include:
·         Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard
·         Compass Drive from Lehigh Avenue to Patriot Boulevard

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

There will be no full roadway closures, the travel delays are expected as the work is performed.

Sunday, July 15, 2018

Project on Hold until Early August due to Events in The Glen

Work Performed:
·         Phase I construction completed along Shermer Road, West Lake Avenue, and The Glen Town Center

Work to be Performed
·         No work is scheduled for the project until after August 6th due to the Park Center Triathlon event the previous weekend.
·         The final phase of construction (Phase II) includes Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard and Compass Road from Patriot Boulevard to Lehigh Avenue.