Friday, August 31, 2018

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, September 4th to September 7th.

 
·       Tentatively starting to mill the project Tuesday Sept. 4
  • once milled the contractor will b e raising structures to apply the final Bituminous Surface
 

 

There will be no full roadway closures, although travel delays are expected as the work is performed.

I would like to say Thank You in advance for your patience.

We would like to wish everyone a safe and happy Labor Day weekend!!



 

 

Friday, August 24, 2018

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, August 27th to August 31st

 
·       Finish lowering structures on Lehigh
  • Tentatively starting to mill the project late next week
 

 

There will be no full roadway closures, although travel delays are expected as the work is performed.

I would like to say Thank You in advance for your patience.

 

Friday, August 17, 2018

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, August 20th to August 24th

 
·       Manhole adjustments throughout Lehigh and Compass
  • Tentatively starting to mill the project late next week
 

 

There will be no full roadway closures, although travel delays are expected as the work is performed.

I would like to say Thank You in advance for your patience.

 

Friday, August 10, 2018

Continuing Curb and sidewalk replacement in phase II



 

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, August 13th to August 17th

 
·        Curb and Gutter and sidewalk removal and replacement WILL continue through the next week.

 

There will be no full roadway closures, the travel delays are expected as the work is performed.

I would like to say Thank You for your patience in advance.

 

Friday, August 3, 2018

Curb, gutter and sidewalk removal and replacement begins next week


Next week the contractor will be installing message signs stating the work on Stage 2 will begin on August 6th.  The road work will begin following the Glenview Park District Triathlon.

 

The roadways included in Stage 2 include:

·        Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard

·        Compass Drive from Lehigh Avenue to Patriot Boulevard

 

Stage 2 work includes concrete curb & gutter replacements, sidewalk replacements, milling the existing asphalt surface, paving a new asphalt surface, pavement striping, and other miscellaneous tasks.

 

Work Anticipated to be performed, August 6th to August 10th

·        Saw cutting of the curbs in stage 2 on Monday August 6.

·        Curb and Gutter and sidewalk removal and replacement starting Tuesday and continuing through the next week to ten days

 

There will be no full roadway closures, the travel delays are expected as the work is performed.

I would like to say Thank You for your patience in advance.