Friday, June 29, 2018

Colored and Stamped Crosswalks and Landscape Restoration On-Going.

Work Performed Last Week, June 25th to June 29th
·         The Glen Town Center
o   Colored and stamped cross-walk installation.
o   Landscape restoration
o   General site clean-up
o   Removal of construction signs
·         West Lake Avenue
o   Completed concrete curb at West Lake and Lily
o   Landscape restoration
o   General site clean-up
o   Removal of construction signs.

Work Anticipated to be performed next week, July 2nd to July 9th  
·         Pavement striping of drive lanes within The Glen Town Center
·         General Site Clean-Up

Due to planned events between July 4th and early August in The Glen area, Stage 2 of the resurfacing will not be started until after August 6th.  We anticipate it will take approximately 2 months to complete this work.  Stage 2 includes Lehigh Avenue from East Lake Avenue Bridge to Patriot Boulevard and Compass Road from Patriot Boulevard to Lehigh Avenue.

Have a save and enjoyable July 4th Holiday.