Friday, August 26, 2016

Phase I Work Nearly Completed. Phase II Asphalt Removal to Begin Following Labor Day Weekend.

Phase I 
Paving Completed along:
·         Chestnut Avenue from Lehigh Avenue to Patriot Boulevard     
·         Patriot Boulevard from East Lake to West Lake Avenue 

West Lake Avenue Paving:
·         Started on Friday, August 26th
·         Anticipated to be completed by Monday, August 29th

Pavement Marking:
·         Chestnut Avenue – Completed
·         Remainder of Phase I (Patriot Boulevard &West Lake Avenue) – Anticipated to be completed week of August 29th

Concrete sidewalk, curb & gutter, and driveway removal and replacement
·         Completed along entire project, Phase I and Phase II

Phase II 
Patriot Boulevard: West Lake Avenue to Willow Road
Patriot Boulevard: Willow Road to Lehigh Avenue
·         Asphalt surface removal to begin following the Labor Day Week on Tuesday, September 6th.

Friday, August 19, 2016

Patriot Boulevard Paving Continues. Chestnut Avenue Completed.

Paving has been completed along Chestnut Avenue from Lehigh Avenue to Patriot Boulevard.

Paving continues along Patriot Boulevard between West Lake Avenue and East Lake Avenue. Unfortunately, due to the rain during the late morning hours on Friday, August 19th, paving operations were suspended for the remainder of the day.

The contractor does anticipate continuing to pave on Saturday, August 20th if substantial rain is not forecasted.

The contractor is hopeful Patriot Boulevard from West Lake Avenue to East Lake Avenue will be paved prior to the school year starting on Tuesday, August 23th.

Tuesday, August 16, 2016

Paving Continues along Chestnut Avenue and Patriot Boulevard. Expect Major Delays

The contractor will continue paving operations this Wednesday, Thursday, Friday, and Saturday (August 17th to 20th) along:
  •  Chestnut Avenue (Lehigh Avenue to Patriot Boulevard) 
  • Patriot Boulevard (West Lake Avenue to East Lake Avenue)
There will continue to be extensive travel delays during working hours. Please be patient and allow for extra time as you travel along the project site.

The goal is to have these roadways paved and fully opened to traffic prior to the start of the school year on Tuesday, August 23rd.

Thanks again for all your patience and understanding.

Friday, August 12, 2016


The Glen Resurfacing Update (Week of August 14):

               Phase I  consisting of:     Chestnut: Lehigh to Patriot         
                                                           Patriot: East Lake to West Lake
                                                           West Lake:  Patriot  to Lake Terrace

               Phase II  consisting of:    Patriot: West Lake to Willow
                                                           Patriot: Willow to Lehigh
                                                        

The contractor will be finished with pavement removal (grinding) of Phase I by Monday, August 15.  The last section to be ground in Phase I will be Patriot Boulevard between West Lake and Chestnut, which will start on Saturday, August 13. 
 

The work on concrete curb and gutter and sidewalk removal and replacement will be completed in Phase I by Tuesday, August 16.  Concrete work in Phase II will continue through the rest of the week.   
 

Final asphalt paving of Phase I  will start Tuesday, August 16, beginning at Chestnut Avenue, and will continue for one week, weather permitting.  Tentative paving scheduled:

               1st location paving – Chestnut
               2nd location paving –Patriot between East Lake and West Lake
               3rd location paving –West Lake

Please note, the paving operation is completed while the roads are open to traffic, therefore expect delays. 

 
Striping of the Phase I will start on Thursday, August 18.
 

Also, on Tuesday morning, August 16 the pavement within Phase I will be coated with oil to provide a bonding surface for the new asphalt.  If it is necessary to drive on fresh oil, please drive slowly to prevent splashing the oil and getting it on vehicles. 

Friday, August 5, 2016

Pavement Removal Begins



The Glen Resurfacing Update:

               Phase I  consisting of:     Chestnut: Lehigh to Patriot          

                                                            Patriot: East Lake to West Lake

                                                            West Lake:  Patriot  to N. Lake Terrace

 

Phase II  consisting of:    Patriot: West Lake to Willow

                                                            Patriot: Willow to Lehigh

                                                           
This week the contractor continued work on concrete curb and gutter removal and replacement in Phase I and Phase II.  Next week the contractor is scheduled to continue replacing curb and gutter and removal and replacement of sidewalk. 

The contractor will start pavement removal (grinding of Phase I only) on West Lake this Saturday, starting at 7am.  Grinding will continue next week: Monday, Tuesday and Wednesday starting on Patriot at West Lake and continue south. 

Paving of the Phase I is tentatively scheduled to start the week of August 14.  More updates to be provided next week.  Thank you.

Major construction has started along the project. There will continue to be extensive travel delays during the working hours, please be patient and allow for extra time as you travel along the project site. We will do everything possible to minimize these delays to the greatest extent possible.
Thanks again for your patience and understanding.

Monday, August 1, 2016

Concrete Curb and Gutter and Sidewalk Removal and Replacement Continues

Work Completed Last Week, July 25th to July 29th
·         Started concrete curb & gutter removal and replacement in Phase I along:
o   Patriot Boulevard – East Lake Avenue to West Lake Avenue
o   Chestnut Avenue – Lehigh Avenue to Patriot Boulevard
o   West Lake Avenue – Patriot Boulevard to North Lake Terrace
·         Site clean-up in preparation for Park Center Triathlon

Work Scheduled to be completed This Week, August 1st to August 5th
Phase I Consisting of:
Patriot Boulevard – East Lake Avenue to West Lake Avenue
Chestnut Avenue – Lehigh Avenue to Patriot Boulevard
West Lake Avenue – Patriot Boulevard to North Lake Terrace
·         Continue concrete curb & gutter removal and replacement
·         Begin concrete sidewalk removal and replacement

Phase II Consisting of:
Patriot Boulevard – West Lake Avenue to Willow Road
Patriot Boulevard – Willow Road to Cardinal Road
Cardinal Road – Patriot Boulevard to Lehigh Avenue
·         Begin concrete curb & gutter removal and replacement
·         Begin concrete sidewalk removal and replacement

Major construction has started along the project. There will continue to be extensive travel delays during the working hours, please be patient and allow for extra time as you travel along the project site. We will do everything possible to minimize these delays to the greatest extent possible.

Thanks again for your patience and understanding.