Friday, September 16, 2016

Asphalt Paving Completed

Phase II Consisting of:
·         Patriot Boulevard – West Lake Avenue to Willow Road
·         Patriot Boulevard – Willow Road to Lehigh Avenue

Work Completed Last week, September 12th to 16th
·         Asphalt surface paving of Phase II Improvements
o   All street paving is now completed for the project.
·         Utility Structure Adjustments
·         Traffic Signal Detector Loop Replacements

Work On-Going:
·         Landscape Restoration
·         Asphalt driveway restoration of those driveways damaged due to construction operations.

Work Anticipated to begin next week, September 19th to 23rd  
·         Pavement Marking
·         General site clean-up

Phase I Consisting of:
·         Chestnut Avenue – Lehigh Avenue to Patriot Boulevard
·         Patriot Boulevard – East Lake Avenue to West Lake Avenue
·         West Lake Avenue – Patriot Boulevard to North Lake Terrace

Work On-Going:
·         Landscape Restoration
·         Asphalt driveway restoration of those driveways damaged due to construction operations.
·         General site clean-up