Phase I Work Nearly Completed. Phase II Asphalt Removal to Begin Following Labor Day Weekend.

Phase I 
Paving Completed along:
·         Chestnut Avenue from Lehigh Avenue to Patriot Boulevard     
·         Patriot Boulevard from East Lake to West Lake Avenue 

West Lake Avenue Paving:
·         Started on Friday, August 26th
·         Anticipated to be completed by Monday, August 29th

Pavement Marking:
·         Chestnut Avenue – Completed
·         Remainder of Phase I (Patriot Boulevard &West Lake Avenue) – Anticipated to be completed week of August 29th

Concrete sidewalk, curb & gutter, and driveway removal and replacement
·         Completed along entire project, Phase I and Phase II

Phase II 
Patriot Boulevard: West Lake Avenue to Willow Road
Patriot Boulevard: Willow Road to Lehigh Avenue
·         Asphalt surface removal to begin following the Labor Day Week on Tuesday, September 6th.