Pavement Removal Begins



The Glen Resurfacing Update:

               Phase I  consisting of:     Chestnut: Lehigh to Patriot          

                                                            Patriot: East Lake to West Lake

                                                            West Lake:  Patriot  to N. Lake Terrace

 

Phase II  consisting of:    Patriot: West Lake to Willow

                                                            Patriot: Willow to Lehigh

                                                           
This week the contractor continued work on concrete curb and gutter removal and replacement in Phase I and Phase II.  Next week the contractor is scheduled to continue replacing curb and gutter and removal and replacement of sidewalk. 

The contractor will start pavement removal (grinding of Phase I only) on West Lake this Saturday, starting at 7am.  Grinding will continue next week: Monday, Tuesday and Wednesday starting on Patriot at West Lake and continue south. 

Paving of the Phase I is tentatively scheduled to start the week of August 14.  More updates to be provided next week.  Thank you.

Major construction has started along the project. There will continue to be extensive travel delays during the working hours, please be patient and allow for extra time as you travel along the project site. We will do everything possible to minimize these delays to the greatest extent possible.
Thanks again for your patience and understanding.