Monday, July 25, 2016

Curb and Gutter Replacement Begins

Work Completed Last Week, July 18th to July 22nd
·         Installation of traffic control devices such as barricades and signs
·         Saw-Cutting of concrete curb & gutter and sidewalk scheduled to be replaced

 Work Scheduled to be completed New Week, July 25th to July 29th
·         Begin concrete curb & gutter removal and replacement in Phase I along:
o   Patriot Boulevard – East Lake Avenue to Chestnut Avenue
o   Chestnut Avenue – Lehigh Avenue to Patriot Boulevard
o   West Lake Avenue – Patriot Boulevard to North Lake Terrace

Major construction associated with this project will begin this week as the concrete curb & gutter and sidewalk replacement begins. Travel delays are expected along the streets they are working on due to construction crews and equipment on-site and working within the parking and travel lanes.  Please use caution and allow for additional time as you drive through the construction zone.

Thank you in advance for your patience and understanding as the construction project begins.